Saturday, 23 August 2008

Building Update

With our last two teams from Hespeler Baptist Church we have framed and supported, installed roofing bricks and rebar on the second floor of our new building. Since the last team left Eduardo and I have installed all of the plumbing and electrical rough-in and framed in what will be an outside access to the three apartments on the second floor. Today we brought in a crew of twelve guys and poured the concrete. Above you can see their cement mixer as well as bucket hoist that they used to get the cement up to the second storey.
This will be left to dry now for the next three weeks and then with our next team, from Forward Baptist Church, we will take down all the forms and supports and begin the columns for the second storey. As mentioned above this building will have three apartments upstairs and the main floor will be used for office space and a workshop.

No comments: